Jungle Gym structure

Dublin Core

Title

Jungle Gym structure

Description

Scheduled timeframe: 13 December 2013 - 9 April 2014

Date

2013

Relation

E000059: Atrium works and specialised structures (is part of);
E000061: Link bridge (Subsequent);

Identifier

E000060

Type

Construction phase event

Event Item Type Metadata

Abstract

The Jungle Gym Structure building element includes:<ul><li>Level 1 - Erect Steel / Dec / Reo (include Temporary […]</li><li>Level 2 - Erect Steel / Deck / Reo - Pour with L</li><li>Level 3 - Erect Steel / Deck / Reo - Pour with L</li><li>Level 4 - Erect Steel / Deck / Reo / Pour</li><li>Connect & Tension Macalloy Hangers / Remove Temp</li><li>Level 5 - Erect Steel / Deck / Reo / Pour</li></ul>