Jungle Gym structure
Dublin Core
Title
Jungle Gym structure
Description
Scheduled timeframe: 13 December 2013 - 9 April 2014
Date
2013
Relation
E000059: Atrium works and specialised structures (is part of);
E000061: Link bridge (Subsequent);
Identifier
E000060
Type
Construction phase event
Event Item Type Metadata
Abstract
The Jungle Gym Structure building element includes:<ul><li>Level 1 - Erect Steel / Dec / Reo (include Temporary […]</li><li>Level 2 - Erect Steel / Deck / Reo - Pour with L</li><li>Level 3 - Erect Steel / Deck / Reo - Pour with L</li><li>Level 4 - Erect Steel / Deck / Reo / Pour</li><li>Connect & Tension Macalloy Hangers / Remove Temp</li><li>Level 5 - Erect Steel / Deck / Reo / Pour</li></ul>
Function
Secondary construction element
Collection
Citation
“Jungle Gym structure,” Melbourne School of Design Building Archive, accessed June 24, 2026, http://archive.msd.unimelb.edu.au/items/show/23312.
