Collection Items
Leighton Irwin Architecture Library
Asbestos removal: 30 October 2012
Japanese Room
Dismantling of the Japanese Room: 20 December 2012
Construction
Revised timeframe: 3 May 2013 - 8 August 2014
Retention to existing facade
Scheduled timeframe: 15 December 2012 - 20 February 2013
Mobilisation of piling rig
Scheduled timeframe: 9 May 2013 - 10 May 2013
Establishment of hardstand for piling rig
Scheduled timeframe: 3 May 2013 - 10 May 2013
Handover to main contractor
Scheduled timeframe: 3 May 2013
Site establishment
Scheduled timeframe: 3 May 2013 - 17 May 2013
Demolition works
Scheduled timeframe - Completed on time: 7 December 2012 - 3 May 2013
Enabling works
Scheduled timeframe: August 2012 - 7 December 2012
Shortlisting
Opening of the competition phase - Site visit and briefing session with competition Respondents and jurors: 26 June 2009
Expressions of Interest entries
First stage of selection process - Call for Expressions of Interest: 27 March 2009 - 1 May 2009
Hoist location
Scheduled timeframe: 29 August 2014 - 28 October 2014
Atrium steel stair
Scheduled timeframe: 6 May 2014 - 9 May 2014
Facade works
Scheduled timeframe: 20 March 2014 - 5 September 2014
External works
Scheduled timeframe: 11 August 2014 - 12 December 2014
Finishes to atrium
Actual timeframe: July 2014 - August 2014
Foundation basement slab works
Scheduled timeframe: 10 August 2013 - 22 October 2013
Retention and excavation
Scheduled timeframe: 25 May 2013 - 29 August 2013
Piling
Scheduled timeframe: 11 May 2013 - 22 June 2013
Excavation, retention and foundation works
Scheduled timeframe: 11 May 2013 - 22 October 2013
Cantilever structure
Scheduled timeframe: 1 May 2014 - 27 May 2014
Main concrete structure
Scheduled timeframe: 19 October 2013 - 5 May 2014
Services and finishes
Scheduled timeframe - Level 3: 2 April 2014 - 4 December 2014
Lift and plant works
Scheduled timeframe: 29 April 2014 - 11 December 2014
Internal cladding
Scheduled timeframe: 7 April 2014 - 5 September 2014
Y-stair structure
Scheduled timeframe: 6 May 2014 - 20 May 2014
Hanging studio steel frame
Scheduled timeframe: 6 May 2014 - 30 May 2014