Scheduled timeframe - Level 3: 2 April 2014 - 4 December 2014
Scheduled timeframe - Level 2: 15 March 2014 - 26 November 2014
Scheduled timeframe - Level 1: 28 February 2014 - 3 December 2014
Scheduled timeframe - Ground floor: 15 February 2014 - 12 December 2014
Scheduled timeframe - Basement: 12 February 2014 - 25 November 2014
Scheduled timeframe - Level 4: 12 April 2014 - 12 December 2014

Date

2014

Relation

E000099: External works (Subsequent);
E000104: Facade works (Previous);
E000115: Construction (is part of);

Identifier

E000070

Type

Construction phase event

Event Item Type Metadata

Abstract

The Services and finishes works are the final steps in the construction process. They cover the basement, ground floor, and Levels 1 - 4.

Notes

BASEMENT: - Services Rough-In and Core Walls - Plantroom - Comms Room - Plantroom - Northern - Plantroom - Pump Room - Plantroom - Switchroom - Plantroom - Southern Plantroom - Large Lecture - Medium Lecture 1 - Medium Lecture 2 - Library - Staff Workspace - Library - Meeting & Project Rooms - Library - Collection - Library - Open Compactus - Amenities - Bin Store, Exhibition Store, Bike Store - Foyer - Completion. GROUND FLOOR: - Services Rough-In and Core Walls - Plant Areas - Workshop - Library - Exhibition - Amenities - Foyer - Completion. LEVEL 1: - Services Rough-In and Core Walls - Dean's Rooms - Northern Rooms (Studio, Studio CAD) - Southern Rooms (Studio, Studio CAD) - Large Seminar Rooms - Studio Hall, Studio - Amenities - Completion. LEVEL 2: - Services Rough-In and Core Walls - IT & Facilities Workspace - Southern Studios & CAD Lab - Hanging Studio - Informal Space on Jungle Gym - Amenities - Completion. LEVEL 3: - Services Rough-In and Core Walls - Northern Workspace Rooms - North-Eastern Workspace Rooms - South-Eastern Workspace Rooms - RHDS (Research Higher Degree Students) Workspace - Prof./Research/Finance/HR/Business Work areas - Hanging Project Research Space - Amenities - Completion. LEVEL 4: - Services Rough-In and Core Walls - Japanese Room - Northern Workspaces - North-Eastern Workspaces - South-Eastern Workspace & Academic - RHDS (Research Higher Degree Students) - Southern Studios - Staff Lounge - Hanging RHDS - Amenities - Completion. At completion of each floor, the following tasks were done: - Services Fit Off Complete - Power On - Commission - Finishes Complete - Install Loose Furniture and Fittings - Defects Inspection, Rectification - Final Sign-Off Floor complete.